Three named Auckland facilities
CDC publicly identifies Silverdale One at 22MW, Hobsonville One at 22MW and Hobsonville Two at 54MW.
Sovereign compute · FULL DEEP TRACKER
A living evidence file tracking CDC’s delivered Auckland capacity, regional pipeline, capital backing, AI readiness, operating footprint and proposed 250MW Stratford expansion.
WHY IT MATTERS
CDC is the clearest operating benchmark against which proposed New Zealand hyperscale projects can be tested. Its delivered capacity, customer demand, energy performance and campus expansion reveal whether New Zealand can convert infrastructure advantages into a durable AI and cloud economy.
CURRENT ASSESSMENT
CDC has three specifically named operating facilities in Auckland: Silverdale Campus One at 22MW, Hobsonville Campus One at 22MW and Hobsonville Campus Two at 54MW. That totals 98MW of named operating capacity. CDC’s separate 220MW-plus Auckland regional figure therefore includes capacity beyond those named operating facilities and should be treated as a regional portfolio or pipeline measure, not current delivered load.
CDC also reports that its New Zealand operation renewed Toitū Enviromark Diamond certification for a fourth consecutive year in August 2026. This strengthens the evidence for an embedded environmental-management system, but it does not replace facility-level disclosure of electricity demand, hour-by-hour emissions, utilisation or the future Stratford project’s impacts.
EVIDENCE GATES
CDC publicly identifies Silverdale One at 22MW, Hobsonville One at 22MW and Hobsonville Two at 54MW.
The larger regional number cannot be presented as current operating capacity without further facility-level disclosure.
CDC is the first hyperscale provider with DGX-Ready certification in New Zealand, but certified Australasian capacity is not disclosed by country.
Infratil reports substantial CDC group operating and construction capacity; those group figures must not be mistaken for New Zealand-only capacity.
CDC reports FY26 electricity matched with renewable supply, WUE below 0.02 at portfolio level, near-zero ongoing cooling-water draw and renewed Toitū Enviromark Diamond certification across its New Zealand data centres for a fourth year.
No reviewed public source establishes facility-level utilisation, tenants, contracted MW or ramp dates for the entire 220MW-plus region.
Contact and CDC intend to seek consent, but both state that neither party has committed to construct the facility.
The project depends on anchor tenants, approvals and project finance, with design and customer engagement still underway.
CAPACITY RECONCILIATION
22MW Silverdale + 22MW Hobsonville One + 54MW Hobsonville Two.
A broader regional figure that includes capacity not yet reconciled to the three named operating facilities.
Approximately 350MW total peak load including ancillary systems, subject to final design and investment gates.
DELIVERY & OPERATING STACK
VERIFIED TIMELINE
STAKEHOLDER MAP
DEPENDENCIES
RISKS & OPEN QUESTIONS
CORE EVIDENCE REGISTER